First Zone of the New Chambacú Complex to be Inaugurated: Dumek Turbay Announces Date
The New Chambacú project is entering its final phase and the countdown to the delivery of its first spaces has begun. With an overall physical progress of 86%, this sports and urban infrastructure work is nearing its service launch, while consolidating key fronts in Major Leagues, urbanism, and complementary venues.
TL;DR
- The New Chambacú project has an 86% overall physical progress.
- The Ligas Menores component is 97% complete and will open on May 15th.
- Ligas Menores includes football fields, access roads, and facilities for children and youth.
- The Ligas Mayores component is 73% complete, with ongoing work on various sports facilities and urbanism.
- The project aims to combine sports, public space, recreation, and urban renewal.
- Currently, the project generates 216 jobs.