Image of the roundabout to be built on Media Luna street in Getsemaní revealed

The recovery of Media Luna street, one of the busiest roads in the Historic Center of Cartagena, enters its final phase and is preparing for its official reopening on May 8, amid announcements of new interventions to improve mobility in the Getsemaní sector.

Image of the roundabout to be built on Media Luna street in Getsemaní revealed

TL;DR

  • Media Luna street in Cartagena's Historic Center will officially reopen on May 8th.
  • The rehabilitation project has reached a 90% completion stage.
  • The street has been paved with 293 meters of terracotta-toned concrete.
  • Installation of prefabricated curbs is at 75%, and sidewalk construction is at 40%.
  • A new roundabout will be built at the intersection of the Heredia bridge separator and El Pedregal.
  • The roundabout aims to reorganize vehicular flows and improve connectivity between various city sectors.
  • The project's investment exceeds 4.6 billion pesos and has created over 50 jobs.