GeoPark begins drilling in Vaca Muerta with investment of up to US$100 million in Neuquén

Portafolio Journalist 03.23.2026 10:17 Updated: 03.23.2026 10:17

GeoPark begins drilling in Vaca Muerta with investment of up to US$100 million in Neuquén

TL;DR

  • GeoPark has started its first drilling campaign in the Vaca Muerta formation in Neuquén, Argentina.
  • The company plans to invest between USD 80 and 100 million in 2026 for this project.
  • The goal is to increase oil production in Argentina from around 1,500 barrels per day to an estimated 5,000-6,000 barrels per day by the end of 2026.
  • GeoPark has partnered with over 30 local contracting companies and signed 40 commercial agreements.
  • The company has established a local office and a team of approximately 30 employees in Neuquén.
  • Medium-term projections aim to increase production in the Neuquén Basin tenfold within three years, reaching nearly 20,000 barrels daily by the end of 2028.