Autoridad Nacional de Licencias Ambientales dio luz verde al Parque Solar Ariguaní
Parque Solar Ariguaní tendrá una capacidad de 200 megavatios Foto: Cortesía: ANLA
TL;DR
- ANLA granted the environmental license for the Ariguaní 200 MW Solar Park.
- The project is located in Chiriguaná, department of Cesar, within the sub-basin of Bajo Cesar.
- It is a photovoltaic plant with 250 MWp peak power and 200 MWac nominal power.
- The project avoids intervention in important natural and semi-natural ecosystems, focusing on pastures and plantations.
- ANLA licensed twelve renewable energy projects in 2025, totaling approximately 2326 MW.
- Prior community consultation was deemed unnecessary for this project.