Bogotá Metro reached 77.53% progress in April and will receive three more trains in May to complete 13 units
Bogotá Metro reached 77.53% progress in April. Photo: Courtesy
TL;DR
- Metro Line 1 has achieved 77.53% overall progress as of April 30, 2026.
- The Bosa workshop yard has a 91.91% completion rate.
- Complementary structures are 99.33% complete, and the viaduct is 85.67% constructed.
- Rolling stock and trains have reached 83.22% completion, with 10 trains already in the city.
- Three more trains will arrive in May, increasing the operational fleet to 13.
- Stations and buildings have reached 37.71% completion, and systems and equipment are at 34.80%.