Progress of works on the Avenida 68 trunk in Bogotá reaches 77.24%

The construction of the Avenida 68 trunk in Bogotá reached an advance of 77.24% as of April 2026. The work, which is part of the mass transit system, is already showing visible changes in several key corridors of the city.

Progress of works on the Avenida 68 trunk in Bogotá reaches 77.24%

TL;DR

  • The Avenida 68 trunk construction in Bogotá is 77.24% complete as of April 2026.
  • The project is divided into five groups, each with specific interventions including stations, bridges, and connections to other transit lines.
  • Group 1 includes three stations, a bridge over Autopista Sur, and a connection to the Metro at Avenida 1 de Mayo.
  • Group 2 features three stations, including one projected to be the busiest, and a bridge at Calle 3.
  • Group 3 involves a vehicular underpass connecting Avenida 68 directly with the Américas trunk.
  • Group 4 adds new stations and a pedestrian underpass at Calle 13.
  • The bridge connecting Calle 26 and Avenida 68, part of Group 5, has been operational since October 2025.