Cartagena regasification plant to go out of service for five days before critical El Niño period
PORTAFOLIO Journalist 10.05.2026 09:21 Updated: 10.05.2026 09:21
TL;DR
- The Cartagena regasification plant, Colombia's only imported gas entry point, will be shut down for five days from July 30 to August 3, 2026.
- The maintenance is scheduled before the anticipated El Niño period to avoid operational disruptions during peak demand.
- The timing was coordinated between the natural gas and electricity sectors, with thermal power plants requesting the earlier maintenance.
- The terminal is crucial for receiving liquefied natural gas (LNG) and supplying thermal power plants, which are important for national energy demand.
- A previous maintenance in October extended due to electrical system failures, highlighting potential risks.
- Colombia's dependence on imported gas is significant, with a portion covering essential demand.
- The Ministry of Mines and Energy must find a way to replace the missing imported gas molecules during the shutdown.
- A contractual dispute with Canacol Energy could further increase the importance of the regasification plant as a backup infrastructure.