TL;DR

  • The José María Córdova airport (MDE) in Antioquia received 14.6 million passengers in 2025, exceeding its installed capacity of 10.5 million.
  • A collective project, 'Región Aeroportuaria Conectada Globalmente,' aims to optimize MDE to 17.5 million passengers, expand it to 23.5 million by 2035, and build a second runway and terminal for over 40 million by 2055.
  • Optimization works at MDE began on April 24th, increasing capacity to 17 million passengers by the end of 2027, but this is a temporary solution.
  • A definitive Airport Master Plan is required to define the second runway and terminal, which is the responsibility of the Aeronáutica Civil.
  • The future of the region's airports depends on a financially viable master plan, which will also address the future of Olaya Herrera, the Apartadó airport, and potential new facilities in other subregions.